Replacing an air handling unit at ground level is mostly an engineering job. Replacing one on a roof, or six floors up in a plant room built before anyone thought about getting plant back out of it, is a logistics job with engineering attached.
Here’s how these projects actually run.
It starts with an access survey
Before anything is specified, we need to know how the old unit comes out and the new one goes in. That means looking at:
- Lift sizes and weight limits, and whether the goods lift reaches the plant floor
- Stairwell widths, turns and headroom
- Door and hatch dimensions along the whole route, not just at the plant room
- Roof access, and whether the roof structure takes the load
- Craneage positions, reach and the ground conditions underneath
- Street access, parking suspensions and permit requirements
The access route decides the unit. We’d rather know that at survey stage than when a lorry arrives.
Craneage, and when it isn’t an option
Craning a unit onto a roof is the quickest route when it works. It needs a crane position with the reach and capacity, somewhere to park it, and usually a road closure or a parking suspension, which means lead time with the local authority.
In a city centre, those conditions often can’t be met. There may be nowhere to site a crane, no road to close, or an oversail over a neighbouring building that nobody will agree to.
Flat-pack as the answer
When the unit can’t be lifted and can’t be carried in assembled, it gets built in place. Sections small enough to fit the lift or stairwell go up individually and the unit is assembled in the plant room.
This is routine work for us. The units at Dalston Cross and the retail complex at Epsom both went in this way, and our flat-pack AHU guide explains the construction.
It’s a decision that has to be made before the unit is built, which is why access belongs in the specification. Our guide to specifying a replacement AHU covers what to include.
Getting the old one out
The existing unit has the same problem in reverse, and it’s often in worse condition than expected. Stripping it down in place is usually the answer: components out first, casing dismantled, everything removed in manageable sections.
Asbestos is a consideration on older plant and needs establishing before anyone starts dismantling.
Sequencing around a working building
Most of this work happens in buildings that carry on operating. The sequence matters:
- Temporary ventilation where the space can’t go without
- Changeovers timed for weekends, shutdowns or quiet periods
- Noisy and disruptive work scheduled around the building’s use
- Services isolated and reinstated in a planned order, not all at once
- A route to get back to working plant if something doesn’t go to plan
We’ve done this in live airport facilities, in occupied offices like Colmore Row and in trading retail buildings. Our guide to ventilation for live operational facilities sets out the approach.
Working at height
Rooftop work brings edge protection, anchor points, weather windows and safe lifting into the programme. Wind stops a crane lift more often than anything else, so the programme needs slack in it rather than a single fixed date.
What the new unit should account for
If you’re replacing a unit in a difficult location, it’s worth using the opportunity:
- Specify for maintenance access, so the next filter change isn’t an ordeal
- Consider an external weatherproof unit if the plant room is the constraint. See external and weatherproof AHUs
- Size for the building as it is now, not as it was. Many units we replace were correct for a layout that changed years ago
- Add heat recovery while the unit is being replaced anyway, which is far cheaper than retrofitting later. See retrofit heat recovery systems
- Plan the components out as well as in, so a coil could be replaced without dismantling the unit
Commissioning and handover
A unit assembled in place still needs commissioning like any other, with airflows set and measured and controls proved. Our guide to AHU commissioning explains why that stage is worth the time.
How we could help
We design, build and install air handling units in restricted and high-level plant rooms across the UK, and we do it in buildings that can’t stop. See our air handling units page, our projects, or our AHU refurbishment services.
Get in touch for an access survey.
Frequently asked questions
Yes. Flat-pack construction lets the unit go up in sections and be assembled in the plant room, which is how we handle most restricted sites.
It depends on access, craneage availability and whether the building stays live. The access and permit side often takes longer than the installation.
Where the space can’t go without, we provide temporary ventilation and sequence the changeover to keep disruption to a minimum.
About the author
Written by Tom Langdell, Director at i-Flow Technologies. Read more about our team on our About Us page: https://i-flowtechnologies.com/about-us/